Service
Installation
Elevator installation covers everything between an empty shaft and equipment cleared for passenger service: survey, equipment selection, mechanical and electrical installation, testing and commissioning. Prawita Karya installs elevators, escalators, home lifts and automated parking systems across Indonesia.

Why installation matters
Installation begins long before anything is lifted into a shaft. The decisive work is the survey and specification, because the shaft dimensions, pit depth, headroom and machine space determine what equipment can physically be installed — and those are usually fixed in concrete by the time anyone looks closely.
On a new build the useful moment is during design, when a traffic analysis can still influence how many shafts are provided and how large they are. On a retrofit the constraint runs the other way: the structure exists, and equipment must be selected to suit it.
Commissioning is the part clients tend to underestimate. Testing safety gear, verifying levelling accuracy, proving door protection and setting the control parameters is what separates a lift that has been installed from one that is fit to carry passengers.
Process
How it works
Site survey
Shaft, pit, headroom and machine space measured, along with power supply and builder's work.
Specification
Equipment selected against traffic demand, building type and the physical constraints found on site.
Installation
Guide rails, machine, car, landing doors and control equipment installed and aligned.
Testing & commissioning
Safety devices tested, levelling and door protection verified, control parameters set.
Handover
Documentation issued and the maintenance programme started.
Scope
What this covers
- Site survey and measured shaft assessment
- Equipment specification and traffic analysis
- Mechanical and electrical installation
- Safety device testing and commissioning
- Documentation and handover
- Transition into a maintenance programme
Why Prawita Karya
What you get
Specified before it is fixed
Constraints identified while they can still be designed around.
Commissioned, not just installed
Safety devices and levelling proven before passenger service.
Continuity into service
The team that commissions the equipment can maintain it.
Products
Equipment we service
FAQ
Common questions
How long does elevator installation take?
Duration depends on the number of units, travel height, equipment type and how ready the builder's work is. Shaft readiness is the most common cause of delay: installation cannot begin until the shaft is complete, true and dry, and power is available.
What does an elevator installation project involve?
A survey, equipment specification, mechanical and electrical installation, testing and commissioning, then handover and the start of a maintenance programme. On a new build the survey ideally happens during design, when shaft provision can still be adjusted.
What needs to be ready before installation starts?
The shaft must be complete and within tolerance, the pit waterproofed, headroom and machine space available, scaffolding or hoisting access arranged, and a suitable power supply present. A pre-installation survey confirms all of this.
Need installation for your building?
Tell us what equipment you have and where it is. Our engineers will tell you what the work actually involves.

